Trade & Manufacturing
Companies Investing in or Moving to the USA
A sourced tracker of 44 companies announcing or building U.S. manufacturing capacity, with each company’s own stated rationale, current status and links, including delays and cancellations.
I’m Peter Klausz, a supply chain professional. This tracker shows what companies have said and what has been verified, and it labels announcements as announcements. It is not an endorsement of any company or policy.

Last updated 2026-10-11. Facts on this page are sourced and dated; analysis is labeled as analysis. Announced investment is not the same as completed investment. General information only, not legal, customs, tax, investment or financial advice. Quotes are verbatim from the cited pages. Where a source gives no policy rationale, the table says so.
What the tracker shows
Across 44 entries, the status picture is mixed: 10 under construction, 9 under way, 5 operating at least in part, 12 announced only, and 8 delayed, paused, restructured or reported cancelled.
Analysis: large, well-capitalized firms in chips, pharmaceuticals, steel, grid equipment and defense show the most visible progress, often with demand drivers such as AI, grid load and munitions contracts. The battery and EV cluster shows the most reversals. Company rationales vary: 6 of 44 entries state no policy rationale in the cited source, and tariffs are discussed explicitly for only five of them (Hyundai, Johnson & Johnson, Mercedes-Benz, Volkswagen and Honda, the last in reporting on a reversed plan).
The Reshoring Initiative, which tracks reshoring and foreign direct investment job announcements, projected about 240,000 jobs announced in 2025, down about 7% from 2024, and noted that it did not include the “$20T of reshoring and FDI projects claimed by the President” (Reshoring Initiative, December 2025). Different trackers count different things, so totals from different sources are not comparable.
| Status | Entries |
|---|---|
| Announced | 12 |
| Under construction | 10 |
| Under way | 9 |
| Operating (in part) | 3 |
| Delayed | 2 |
| Operating | 2 |
| Restructured / unfavorable | 2 |
| Paused / unfavorable | 2 |
| Operating (delayed) | 1 |
| Reported cancelled / unfavorable | 1 |
Semiconductors & electronics
| Company | Industry | Announced investment or move | Location | Date | Stated rationale (company’s own words) | Status as of 2026-10-11 | Sources |
|---|---|---|---|---|---|---|---|
| Apple | Consumer electronics | $600B U.S. commitment over four years, including the American Manufacturing Program (AMP) with U.S. suppliers | Nationwide, incl. Houston, TX | 2025-08-06 (raised); updates 2026-02-24 and 2026-08-13 | Tim Cook: “we’re grateful to the President for his support.” The release says AMP will “incentivize global companies to manufacture even more critical components in the United States.” No tariff statement in the release. | Partly under way: Houston training center opened 2026-08-13; the $600B is a multi-year pledge, not verified spending | Announcement or source · Status source |
| Broadcom (Apple supplier) | Semiconductors | Apple multiyear agreement “expected to exceed $30 billion”; more than 15 billion U.S.-made chips; Fort Collins, CO facility expansion | Fort Collins, CO | 2026-07-08 | Apple release: Apple has been working “with the administration and businesses across the U.S. to help create an end-to-end silicon supply chain in America.” | Announced (agreement and expansion) | Announcement or source |
| TSMC | Semiconductors | $265B total Arizona plan per TSMC (six logic fabs, two advanced-packaging facilities, R&D center, plus more announced July 2026) | Phoenix, AZ | 2026-07 (latest expansion; site chosen 2020) | TSMC: new fabs announced “to support strong US customer demand.” | Fab 1 operating (N4 volume production since Q4 2024); Fab 2 volume production on N3 targeted 2H 2027; Fab 3 under construction; Fab 4 and first packaging fab in early construction | Announcement or source |
| Micron | Memory chips | More than $250B in planned U.S. investment through 2035 | Boise, ID; Clay, NY; Virginia | 2026-07-09 | Micron: “driven by surging demand for memory in the AI era.” The release also says Micron will “remain disciplined” and “responsive to the market environment.” | Under construction: NY first concrete poured July 2026; Idaho first-fab wafer output expected mid-2027 (company expectation) | Announcement or source |
| Intel (Ohio One) | Semiconductors | More than $28B for two leading-edge fabs | New Albany, OH | Timeline revised 2025-02-28 | Intel: aligning fab production start “with the needs of our business and broader market demand.” | Delayed: Mod 1 operations 2030–2031, Mod 2 2032 (Intel, Feb 2025). A local report dated 2026-08-26 says the fab is still set to open by 2031 | Announcement or source · Status source |
| NVIDIA | AI computing hardware | “Up to half a trillion dollars of AI infrastructure” produced in the U.S. within four years through partners (production value with partners, not NVIDIA’s own capital spending) | Arizona, Texas | 2025-04-14 | NVIDIA: partners are “expanding their global footprint and hardening supply chain resilience.” | Partly under way: partner plant in Fort Worth producing NVIDIA systems (NVIDIA blog 2026-08-05); the four-year target is a plan | Announcement or source · Status source |
| Wistron (NVIDIA supplier) | Electronics manufacturing | NVIDIA blog cites “a combined $700 million commitment to U.S. advanced manufacturing”, 500+ jobs rising to 1,000 by end of 2026 | Fort Worth, TX | 2026-08-05 | Jensen Huang (NVIDIA): building plants in the U.S. “has allowed the United States to really reindustrialize for the first time in a long time.” | Operating: producing GB300 systems and preparing Vera Rubin production (per NVIDIA) | Announcement or source |
| Texas Instruments | Analog semiconductors | More than $60B across seven fabs and three mega-sites | Texas (incl. Sherman) and Utah | 2025-06-18 | Haviv Ilan (TI CEO): “TI is building dependable, low-cost 300mm capacity at scale.” The release says TI is “working with the Trump administration.” | Partly operating: Sherman SM1 began production 2025-12-17 and ramps with customer demand; later fabs not verified as built | Announcement or source · Status source |
| GlobalFoundries | Semiconductors | $16B U.S. investment (headline: “to Reshore Essential Chip Manufacturing”) | Malta, NY; Vermont | 2025-06-04 | Company headline: reshore “essential chip manufacturing and accelerate AI growth.” | Announced; later company release says volume interposer production for AI packaging is expected to ramp at Malta in 1H 2028 | Announcement or source · Status source |
| Samsung Electronics | Semiconductors | Taylor, TX fab (total investment figure not verified for this tracker) | Taylor, TX | 2026-09-16 (report) | No policy rationale stated in the cited source. | Early production: trial production of Tesla AI chips reported by Seoul Economic Daily; volume supply reported as expected in 2027 | Announcement or source |
| SK hynix | HBM memory packaging | More than $4B advanced packaging fab | West Lafayette, IN | 2026-08-28 (groundbreaking) | SK hynix: to “help stabilize the U.S. semiconductor supply chain and contribute to strengthening U.S. national security and economy.” | Under construction: cleanroom due October 2028; next-generation HBM mass production planned 2H 2029 | Announcement or source |
| Amkor | Chip packaging and test | $7B (2025-10-06) raised to $12B (2026-09-08) | Peoria, AZ | 2025-10-06; 2026-09-08 | Amkor: phase 2 “[d]riven by strong customer commitments.” | Under construction (phase 2 announced) | Announcement or source |
| Wolfspeed | Silicon carbide semiconductors | Earlier U.S. expansion plans (investment figure not verified for this tracker) | North Carolina | 2025-09-29 (restructuring completed) | Company: a “Growth Plan to Leverage Installed 200mm Capacity.” | Restructured: emerged from Chapter 11 on 2025-09-29, cutting debt about 70% (company); expansion pace slowed | Announcement or source |
Pharma & life sciences
| Company | Industry | Announced investment or move | Location | Date | Stated rationale (company’s own words) | Status as of 2026-10-11 | Sources |
|---|---|---|---|---|---|---|---|
| Eli Lilly | Pharmaceuticals | $50B push to reshore medicine production; Houston API site $6.5B; ten U.S. sites announced since 2020 | Houston, TX (plus VA, AL, PA and others) | 2026-09-21 (Houston groundbreaking) | Lilly: “to meet growing demand at home and export American-made medicines to people around the world.” | Under construction (Houston groundbreaking 2026-09-21) | Announcement or source |
| Johnson & Johnson | Pharma / medtech | $55B in U.S. manufacturing, R&D and technology investment by early 2029; two additional facilities announced (North Carolina and Pennsylvania) | Wilson, NC; Pennsylvania | 2026-01-08 (release); 2026-01-09 (NC announcement) | J&J’s release was issued alongside a voluntary agreement with the U.S. government on medicine access and costs; it says J&J “Delivers on U.S. Manufacturing and Innovation Investments” (headline). | Under construction: $2B Wilson, NC biologics plant (company release); two additional facilities announced | Announcement or source · Status source |
| Roche / Genentech | Pharmaceuticals | $50B Roche U.S. commitment; Holly Springs, NC facility first >$700M, later about $2B | Holly Springs, NC | 2025-08-25 (groundbreaking); 2026-01-20 (expanded) | Genentech’s Magargee: “We are supportive of President Trump’s goal to bring more pharmaceutical manufacturing to the United States.” | Under construction (topping-out milestone 2026-08-18) | Announcement or source · Status source |
| AstraZeneca | Pharmaceuticals | $50B investment in U.S. medicines R&D and manufacturing; $4.5B Virginia facility, 3,600 jobs (company figure) | Albemarle County, VA | 2025-10-09 | AstraZeneca release: the investment “offers assurance from a national security and health sovereignty perspective.” | Under construction (groundbreaking 2025-10-09; operations years away) | Announcement or source |
| Novartis | Pharmaceuticals | $23B over five years; seven new U.S. facilities | Multiple states, incl. NC | 2026-04-30 (plan finalized) | Vas Narasimhan (CEO): “strengthening our ability to locally develop, produce, and deliver medicines at scale.” | Progressing: company says all components of the plan have progressed | Announcement or source |
| AbbVie | Pharmaceuticals | $100B in U.S. R&D and capital over a decade; $1.4B Durham, NC campus (734 jobs) | Durham, NC | 2026-04-22 | Robert Michael (CEO): “strengthening our ability to support future medical breakthroughs.” | Announced; construction begins 2026, completion expected by end of 2028 | Announcement or source |
| Merck | Pharmaceuticals | More than $70B in U.S. R&D and capital beginning 2025; $3B Elkton, VA facility | Elkton, VA | 2025-10-20 | Robert Davis (CEO): the investment “helps advance our goal of providing new, innovative treatment options.” | Under construction (start of construction 2025-10-20) | Announcement or source |
| Amgen | Biotechnology | Additional $300M; company says nearly $2B in U.S. manufacturing investment over the last year | Juncos, Puerto Rico (U.S. territory) | 2026-05 | Robert Bradway (CEO): “this expansion reflects our continued commitment to American manufacturing.” | Announced | Announcement or source |
| GSK | Pharmaceuticals | $30B in U.S. R&D and manufacturing over five years, incl. $1.2B (biologics flex factory, Upper Merion, PA) | Pennsylvania and other sites | 2025-09-17 | GSK: “developing and making products in the United States for the United States.” | Announced; release said construction at Upper Merion was planned to begin in 2026 (not verified as started) | Announcement or source |
Autos & batteries
| Company | Industry | Announced investment or move | Location | Date | Stated rationale (company’s own words) | Status as of 2026-10-11 | Sources |
|---|---|---|---|---|---|---|---|
| Hyundai Motor Group | Automotive | $26B U.S. investment through 2028 (per Hyundai CEO) | Georgia, Louisiana and others | Statement 2026-08-20 | José Muñoz (Hyundai CEO): “the USA is the most important market in the world besides Korea.” On tariffs, CNBC quotes him: “Tariffs are helping accelerate our localization plan.” | Under way: Georgia Metaplant operating; CEO says a capacity increase to 700,000–800,000 units by 2028 is being considered (not confirmed) | Announcement or source |
| Hyundai Steel | Steel (automotive supply) | $5.8B electric-arc-furnace steel mill, 2.7M metric tons per year | Louisiana | 2026-09-04 (project launch) | Euisun Chung (Hyundai Motor Group): “As America strengthens its manufacturing leadership, steel will continue to power the next chapter of its industrial resurgence.” | Under construction; commercial production targeted 2029 | Announcement or source |
| Stellantis | Automotive | $13B U.S. plan (headline: “to Grow in the United States”); Belvidere, IL investment raised to more than $800M | Belvidere, IL and others | 2025-10 (plan); 2026-08-14 (Belvidere update) | No policy rationale stated in the cited source. | Delayed: Belvidere pilot production now expected 1H 2028 and retail production 2H 2029, versus 2027 previously; more than $60M spent through July 2026 | Announcement or source · Status source |
| General Motors | Automotive | $4B in three U.S. plants (headline: “GM to invest $4 billion in its U.S. manufacturing plants”); +$275M at Spring Hill, TN (2026-06-24) | Orion, MI; Fairfax, KS; Spring Hill, TN | 2025-06-10; 2026-06-24 | No policy rationale stated in the cited source. | Under way (investments continuing; Spring Hill addition announced 2026-06-24) | Announcement or source · Status source |
| GM / Samsung SDI joint venture | EV batteries | $3.5B battery project | New Carlisle, IN | 2026-05-14 (report) | Indiana Economic Development Corporation spokesperson (not the companies): “The project is being paused.” | Paused (EV demand recalibration, per the report) | Announcement or source |
| Ford / BlueOval SK | EV batteries | Joint venture dissolved; Ford took full ownership of two Kentucky battery plants, SK On took the Tennessee plant | Glendale, KY; Stanton, TN | 2026-05-22 (report) | SK On Tennessee spokesperson: the company “looks forward to supplying batteries for its future electrified vehicles.” | Restructured: Kentucky plant idled while Ford transitions to energy-storage batteries (WKYU, 2026-02-09); SK On plans production at Stanton from 2028 | Announcement or source · Status source |
| Panasonic Energy | EV batteries | De Soto, KS plant (about $830M in Kansas tax credits per the report) | De Soto, KS | 2026-06-17 (report) | No policy rationale stated in the cited source. | Operating, ramp-up delayed; some capacity being converted for data-center batteries (report) | Announcement or source |
| Toyota | Automotive | Up to $10B additional U.S. investment over five years; $1B first phase | Kentucky; Indiana (first phase) | 2025-11-13; 2026-03-24 | Mark Templin (Toyota COO): investment is “tied to our philosophy of building where we sell and buying where we build.” | Announced; first $1B phase announced 2026-03-24 | Announcement or source · Status source |
| Mercedes-Benz | Automotive | $7B in the U.S. by 2030, including $4B for a new GLC line | Tuscaloosa, AL | 2026-03-31 (announcement); 2026-04-03 (MotorTrend) | Michael Schiebe (Mercedes board): “The U.S. is such an important market for us and the GLC is such an important car for the U.S. market, so it only makes sense to produce the car here in the U.S.” MotorTrend reports tariffs were part, but not all, of the reason. | Announced; GLC production expected to begin in 2029 | Announcement or source |
| Volkswagen (Audi U.S. plant) | Automotive | Proposed Audi plant in the United States | United States (site not selected) | 2026-01-25 | Oliver Blume (VW CEO): “Given an unchanged tariff burden, large additional investment cannot be funded.” | Paused: plant plan at risk unless tariffs fall (CEO, January 2026). Later press reports of a board review were not verified | Announcement or source |
| Honda | Automotive | Planned next-generation Civic production in Greensburg, IN, reported cancelled | Greensburg, IN | 2026-10-11 (report) | No policy rationale stated in the cited source. | Reported cancelled by a trade-press article; company confirmation was not seen in the cited source | Announcement or source |
Industrial, appliances & grid equipment
| Company | Industry | Announced investment or move | Location | Date | Stated rationale (company’s own words) | Status as of 2026-10-11 | Sources |
|---|---|---|---|---|---|---|---|
| GE Appliances | Home appliances | More than $3B over five years, modernizing 11 plants; +$1B in Louisville announced 2026-09 | Kentucky, Alabama, Georgia, Tennessee, South Carolina | 2025-08-13; 2026-09-02 | Kevin Nolan (CEO): “our $3 billion, five-year plan shows that our commitment to U.S. manufacturing will continue into the future.” The release describes ranges previously made in Mexico moving to the U.S. | Under way (insourcing and plant upgrades; first Camden, SC phase due early 2026) | Announcement or source · Status source |
| Whirlpool | Home appliances | $60M new component facility, up to 150 jobs | Perrysburg, OH | 2026-04-10 | Marc Bitzer (CEO): “When there is a level playing field, our American workers can out-compete anyone in the world.” | Announced | Announcement or source |
| Caterpillar | Heavy equipment | About $1B to expand Cat Compact manufacturing | Sanford, NC | 2026-09-30 | Rod Shurman (Caterpillar): “As demand for compact equipment continues to increase, we’re investing to better serve this growing segment of customers.” | Announced (“intends to invest”) | Announcement or source |
| GE Aerospace | Aerospace | $1B across 30+ communities in 17 states (second consecutive $1B); plans 5,000 U.S. hires | 17 states | 2026-03-09 | Larry Culp (CEO): “Maintaining U.S. aerospace leadership requires sustained investment in our people, our facilities, and the technologies that will define the future of flight.” | Announced / ongoing annual program | Announcement or source |
| Hitachi Energy | Grid equipment | $457M large power transformer plant, about 825 jobs | South Boston, VA | 2026-06-29 (groundbreaking) | Company release: the project “[s]trengthens Virginia’s role in producing equipment essential to a reliable, resilient electric grid as energy demand skyrockets.” | Under construction | Announcement or source |
| Siemens | Electrical equipment | More than $200M in Pendergrass, GA and Grand Prairie, TX (1,500+ jobs); $30M Prince George, VA switchgear site (operated by Jabil) | Georgia, Texas, Virginia | 2026-08-07; 2026-05-27 | Ann Fairchild (Siemens USA CEO): “There is unprecedented demand for critical infrastructure here in the U.S.” | Announced | Announcement or source · Status source |
Metals
| Company | Industry | Announced investment or move | Location | Date | Stated rationale (company’s own words) | Status as of 2026-10-11 | Sources |
|---|---|---|---|---|---|---|---|
| Nippon Steel / U.S. Steel | Steel | About $11B in new investment in U.S. Steel by 2028 under a National Security Agreement | Pennsylvania, Illinois and others | 2025-06-18 | Commitment made under a National Security Agreement with the U.S. government (company release). | Under way: Granite City Blast Furnace B restarted 2026-03-30; Mon Valley hot strip mill slated for 2029 | Announcement or source · Status source |
| Nucor | Steel | $4B sheet mill; separate $105M Indiana utility-structures expansion | West Virginia; Crawfordsville, IN | 2026-08-27 (WV status); 2026 (Indiana release) | Leon Topalian (CEO, Indiana expansion): “the strong demand we are seeing in the utility market.” | Commissioning: first arc struck in the West Virginia melt shop (trade press, 2026-08-27) | Announcement or source · Status source |
| Cleveland-Cliffs | Steel | $1B Middletown Works modernization, supported by a $500M U.S. DOE award | Middletown, OH | 2026-08-21 | Lourenco Goncalves (CEO): “Cleveland-Cliffs is making a decisive investment in the future of American steelmaking and manufacturing.” | Announced; blast-furnace rebuild completion planned Q1 2030 | Announcement or source |
Defense
| Company | Industry | Announced investment or move | Location | Date | Stated rationale (company’s own words) | Status as of 2026-10-11 | Sources |
|---|---|---|---|---|---|---|---|
| Anduril | Defense | Arsenal-1 production campus | Pickaway County, OH | 2025-01-16 (announced); Fury production began 2026-03; first Ohio-built Fury 2026-07-27 | No policy rationale stated in the cited source. | Operating: Fury production under way | Announcement or source |
| Lockheed Martin | Defense | $8–$9B through 2030 to modernize 20+ U.S. facilities and scale munitions output | 20+ U.S. facilities, incl. Troy, AL | 2026 | Dan Nimblett (Lockheed): “We are moving with speed to support the Department of War’s Arsenal of Freedom.” Plans to triple PAC-3 MSE capacity by end of 2030 under a contract of up to $53.86B. | Under way (groundbreakings held; contract-backed) | Announcement or source |
Unfavorable and cautionary updates
These are the entries where the cited sources report a delay, pause, restructuring or reported cancellation. They matter because they show why announcements are not delivery.
- **Intel (Ohio One):** Delayed: Mod 1 operations 2030–2031, Mod 2 2032 (Intel, Feb 2025). A local report dated 2026-08-26 says the fab is still set to open by 2031.
- **Wolfspeed:** Restructured: emerged from Chapter 11 on 2025-09-29, cutting debt about 70% (company); expansion pace slowed.
- **Stellantis:** Delayed: Belvidere pilot production now expected 1H 2028 and retail production 2H 2029, versus 2027 previously; more than $60M spent through July 2026.
- **GM / Samsung SDI joint venture:** Paused (EV demand recalibration, per the report).
- **Ford / BlueOval SK:** Restructured: Kentucky plant idled while Ford transitions to energy-storage batteries (WKYU, 2026-02-09); SK On plans production at Stanton from 2028.
- **Panasonic Energy:** Operating, ramp-up delayed; some capacity being converted for data-center batteries (report).
- **Volkswagen (Audi U.S. plant):** Paused: plant plan at risk unless tariffs fall (CEO, January 2026). Later press reports of a board review were not verified.
- **Honda:** Reported cancelled by a trade-press article; company confirmation was not seen in the cited source.
Analysis: several reversals are in EV batteries, where the 2025 tax-law changes ended the new clean vehicle credit for vehicles acquired after 2025-09-30 (IRS FAQ). Others reflect company-specific demand or cost choices, such as Intel’s alignment of fab timing with demand and Volkswagen’s tariff-cost argument.
Method and caveats
- **What I included:** companies with a public, dated announcement and a primary source (company release, SEC filing, government release) or a named trade-press report, covering semiconductors, pharmaceuticals, autos and batteries, industrial and grid equipment, metals and defense.
- **Rationale column:** quotes or close attributed paraphrases of what the company said in the cited page. I did not infer motives. “No policy rationale stated in the cited source.” means exactly that.
- **Dollar figures:** as stated by the company or source, usually multi-year, and often including research and development and spending already planned. They are not audited and cannot be summed.
- **Status:** announced (publicly stated, no verified construction), under construction, under way (programs in progress), operating (production reported), delayed, paused, restructured, or reported cancelled. Status comes from the cited pages on 2026-10-11.
- **Secondary sources:** Samsung, Honda, Panasonic, Ford/BlueOval SK, GM/Samsung SDI, Stellantis (status) and Volkswagen rely on press or trade reports rather than company releases, and are labeled as such.
- **Blocked pages:** a few company pages block automated fetching (Intel, GlobalFoundries, Stellantis and GM). I confirmed their headlines through search indexes and used other dated pages for status.
- **Not covered:** state-level incentives, small-company announcements, and investment that happened without a public announcement.
This tracker is general information, not investment advice. Included companies have not reviewed or endorsed this page.
Frequently asked questions
Does an announced investment mean the money has been spent?
No. Announced figures are usually multi-year company commitments that can include research and development, equipment, existing spending or plans contingent on demand. This tracker lists a status for each entry, and many are still announced or under construction. Micron, for example, said it would stay “disciplined” and “responsive to the market environment.”
Why does the tracker include delays and cancellations?
Because a one-sided list would be misleading. Intel’s Ohio fabs, Stellantis’ Belvidere plant, the GM and Samsung SDI battery project, Ford’s BlueOval SK venture, Volkswagen’s Audi plant and a reported Honda change are included with sources.
Are tariffs the reason companies are investing in the U.S.?
In the sources cited here, companies give varied reasons: customer demand, proximity to customers, national security, government relationships and, in a few cases, tariffs. Of the 44 entries, 6 have no policy rationale stated in the cited source. Tariffs are discussed explicitly in the cited material for Hyundai, Johnson & Johnson (a tariff-exemption agreement), Mercedes-Benz, Volkswagen and, in reporting on the reversed Civic move, Honda. Elsewhere the cited pages mention tariffs only in forward-looking risk language or not at all.
How was the list chosen?
It is not a census or a ranking. I selected companies with public, sourced announcements across semiconductors, pharmaceuticals, autos and batteries, industrial and grid equipment, metals and defense, and I included both favorable and unfavorable updates. Smaller companies and announcements without reliable sources are not covered.
How current is the data?
Statuses were checked on 2026-10-11 against the cited pages. Projects change quickly, so use the links to check the latest status.
Can you add or correct an entry?
Yes. If you represent a company or see an error, use the contact page with a link to a primary source, and I’ll review it.
Related pages
Restoring U.S. Manufacturing
Reshoring drivers, policy tools, constraints and what it means for small manufacturers.
Trade Wars and Tariffs: Current State
Timeline, legal status and a practical sourcing playbook.
Working through these issues in your own supply chain? See Manufacturing Procurement & Supply Chain Services, Statadventure (supply chain software in Python and SQL), the Supply Chain Knowledge Base, all services, or get in touch.
Sources
Every figure above comes from one of these sources, with the as-of date shown in the text. Links were checked on 2026-10-11.
- Reshoring Initiative, December 2025 E-News Part II (2025 jobs projection)
- Internal Revenue Service, FAQs on modification of Sections 25C, 25D, 25E, 30C, 30D, 45L, 45W and 179D under Public Law 119-21
- Apple: announcement or source and status source
- Broadcom (Apple supplier): announcement or source
- TSMC: announcement or source
- Micron: announcement or source
- Intel (Ohio One): announcement or source and status source
- NVIDIA: announcement or source and status source
- Wistron (NVIDIA supplier): announcement or source
- Texas Instruments: announcement or source and status source
- GlobalFoundries: announcement or source and status source
- Samsung Electronics: announcement or source
- SK hynix: announcement or source
- Amkor: announcement or source
- Wolfspeed: announcement or source
- Eli Lilly: announcement or source
- Johnson & Johnson: announcement or source and status source
- Roche / Genentech: announcement or source and status source
- AstraZeneca: announcement or source
- Novartis: announcement or source
- AbbVie: announcement or source
- Merck: announcement or source
- Amgen: announcement or source
- GSK: announcement or source
- Hyundai Motor Group: announcement or source
- Hyundai Steel: announcement or source
- Stellantis: announcement or source and status source
- General Motors: announcement or source and status source
- GM / Samsung SDI joint venture: announcement or source
- Ford / BlueOval SK: announcement or source and status source
- Panasonic Energy: announcement or source
- Toyota: announcement or source and status source
- Mercedes-Benz: announcement or source
- Volkswagen (Audi U.S. plant): announcement or source
- Honda: announcement or source
- GE Appliances: announcement or source and status source
- Whirlpool: announcement or source
- Caterpillar: announcement or source
- GE Aerospace: announcement or source
- Hitachi Energy: announcement or source
- Siemens: announcement or source and status source
- Nippon Steel / U.S. Steel: announcement or source and status source
- Nucor: announcement or source and status source
- Cleveland-Cliffs: announcement or source
- Anduril: announcement or source
- Lockheed Martin: announcement or source