The Institute for Supply Management (ISM) Manufacturing PMI is a monthly signal many manufacturers already receive, and one that is easy not to translate into a planning action. This guide explains how to read it in an S&OP meeting. Selected figures come from the October 2026 ISM Manufacturing PMI Report, issued November 2, 2026. Use that official page for the full tables. The figures cited here are limited factual points, with a link to the source.
If you are still standing up a monthly planning rhythm, start with S&OP in plain English.
This post is general education, not legal, customs, tax, financial or compliance advice. Confirm details with a licensed professional and the official sources linked below.
What the Manufacturing PMI measures
ISM describes the Manufacturing PMI as a composite index based on five equally weighted diffusion indexes: New Orders, Production, Employment, Supplier Deliveries and Inventories. New Orders, Production, Employment and Inventories are seasonally adjusted. A reading above 50 percent indicates that the manufacturing sector is generally expanding; a reading below 50 percent indicates that it is generally contracting. ISM also states that a Manufacturing PMI above 47.5 percent, over a period of time, generally indicates expansion in the overall economy.
One of the five components is easy to misread. Supplier Deliveries is inverted: a reading above 50 percent means deliveries are slower, which ISM notes is typical as demand increases. In a planning meeting, treat a high Supplier Deliveries reading as a lead-time and expedite signal, not as a sign that suppliers are “doing better.”
The November 2, 2026 report said the Manufacturing PMI registered 55.5 percent in October, 1.0 percentage point above September’s 54.5 percent, and that manufacturing activity expanded for a 10th consecutive month. The same report said the Production Index registered 59 percent, its highest reading since November 2021.
How to use the report in S&OP
Do not argue about a one-tenth move in the headline number. Use a short, repeatable set of questions that connect the published indexes to your own plan.
1. Demand: orders, backlogs and customers’ inventories
New Orders, Backlog of Orders and the Customers’ Inventories Index are the demand side of the report. In October, ISM reported New Orders at 55.5 percent, Backlog of Orders at 54.6 percent, and Customers’ Inventories at 41.6 percent. ISM treats a Customers’ Inventories reading below 50 percent as “too low,” and said that a “too low” status is usually considered positive for future production. Compare those signals with your own order book and with the forecast process in demand forecasting basics. If customers in your industry are running lean, a strong month of bookings may still be followed by short-notice releases.
2. Supply: deliveries, prices and stated lead times
ISM reported that the Supplier Deliveries Index registered 59.1 percent in October, the 11th consecutive month in “slowing” territory. The Prices Index registered 75.2 percent, the 25th straight month of increasing prices, though that was 2.7 percentage points below September’s 77.9 percent. The report’s buying-policy table said the average commitment lead time for production materials was 87 days in October, three days longer than in September. Bring those figures next to your own quoted, confirmed and actual lead times; the method for keeping those dates distinct is in Supplier Lead Time Data.
3. Inventories: the national index versus your own stock
The Inventories Index registered 51.4 percent in October, up 2.8 percentage points from 48.6 percent in September, returning to expansion. A national diffusion index does not tell you whether your plant is carrying too much or too little of a given part. Use it as context for the turns and days-on-hand measures in Inventory Turns and Days on Hand, not as a substitute for them.
A 15-minute agenda item
In the S&OP pack, devote one page to three lines: the latest Manufacturing PMI and its five components; your own new-order, lead-time and inventory measures for the same month; and any commodities the report lists as up in price or in short supply that you actually buy. In October, ISM listed electronic components, memory, printed circuit boards, electrical components and several steel and copper items among those in short supply. Then decide whether any safety stock, order policy or supplier conversation should change before the next cycle.
Frequently asked questions
Is a Manufacturing PMI above 50 percent good news for my plant?
It means ISM’s panel reported expansion in manufacturing overall, not that every industry or every company expanded. The October report listed 12 industries in growth and three in contraction. Always read the industry lists, not only the headline.
Why can Supplier Deliveries rise while other indexes also rise?
Because the deliveries index is inverted. In an expansion, slower deliveries often arrive with stronger orders and production. For planning, a rising deliveries index is a warning about lead time, not a second confirmation of growth.
Additional sources
- ISM: October 2026 Manufacturing PMI Report (issued November 2, 2026)
- ISM: October 2026 Manufacturing at a Glance PDF
- Institute for Supply Management
Peter Klausz is an MBA (University of Rochester, Simon Business School) and the founder of Statadventure, LLC, which has built supply chain software in Python and SQL since 2018. He previously managed F100 engine supply chain work at Pratt & Whitney. Based in Burlington, Massachusetts, he is open to contracting and new roles. Get a Quote.